Kentucky OS/OW Permit Requirements

United States ยท KYTC โ€” Division of Motor Carriers, Permit Branch

Everything heavy-haul carriers need to know before moving an oversize or overweight load through Kentucky: survey triggers, fees, lead times and the official permit portal.

Lead time
3 business days
Base fee
$40 single-trip; $500 annual
Permit validity
Up to 5 days

Route survey triggers

  • Height
    Height exceeds 13'6" โ€” oversize permit required
  • Width
    Width exceeds 8'6" โ€” oversize permit required
  • Length
    Length exceeds 65' โ€” oversize permit required
  • Weight
    Gross weight exceeds 80,000 lbs โ€” overweight permit required
  • Width
    Width exceeds 16' โ€” route survey required
  • Height
    Height exceeds 15' โ€” route survey required
  • Weight
    Gross weight exceeds 200,000 lbs โ€” KYTC special heavy haul permit

Fee notes

Single-trip $40. Annual permits $500. Coal/extra-heavy overweight surcharge $0.0285/ton-mile (KRS 281.762 Extended Weight Coal Haul). Superload engineering review $500+ depending on bridges along route.

Official resources

Reference information last verified May 2026. Always confirm current requirements with KYTC โ€” Division of Motor Carriers, Permit Branch.